CIP 3321 - Westgate Drive Intersection

Westgate Drive/Cedar Hills Boulevard/Dawson Way Intersection Realignment

Project Description: Realign the intersection of Dawson Wy and Westgate Dr with Cedar Hills Blvd. Work includes intersection signalization, continuation of a 5-lane arterial cross section on Cedar Hills Blvd, and a 2-lane collector cross section on Westgate Dr and Dawson Wy. At the new intersection, street improvements on Westgate Dr and Dawson Wy include two twelve-foot through lanes, a left turn lane in each direction, and an eastbound right turn lane. Beyond the intersection, Dawson Wy and Westgate Dr will both be built within a 60 foot right of way and include two twelve-foot travel lanes with sharrows, eight-foot parking lanes, and 6'-10' sidewalks.

Project Manager: Jim Brink, 503-526-2450

Project Status: 

FY11-12: Completed survey of Cedar Hills Blvd/Westgate Dr/Dawson Wy intersection.

FY12-13: Study alignment options. 

FY13-14: City staff begins preliminary design and budget estimates.

FY14-15: City staff continues preliminary design and budget estimates.

FY15-16: Contract with David Evans & Associates (DEA) approved 3-1-16. NTP issued to DEA to begin design on 3-16-16.

FY16-17: Completed 60% design on 2-16-17. Completed 90% design on 3-31-17. Completed potholing on 4-18-17.

FY17-18: Completed supplementary survey at driveways and Goodwill entrance on 8-17-17. Complete right of way acquisition and land use.

FY18-19: Complete construction.

Substantial Completion Date:  October 30, 2018

CIP 3321 Description

SW Cedar Hills Blvd street scene near by Carr Nissan dealership.