Site Development Engineering Review & Inspection Fees
Site Development Permit Fees • Erosion Control Fees

Site Development Engineering Review &
Inspection Fees

Effective July 1, 2005

Research Fee $50.00
FEMA Floodplain Elevation Determination Fee
(per tax lot)
$25.00
Floodplain, Floodway and Wetland Modification Fee $500.00 per permit
House Move Permit Fee $100.00 per section
Re-Inspection Fee $50.00
Right-of-Way (ROW) and Facilities Permit Application Fee
Individual tree cut (street tree); sidewalk repair, replacement, or installation; street cut
$75.00
Engineering Review of Building Permit Plans Fee $40.00 per permit

[ TOP ]

Site Development Permit Fees

Site Development Application Fee
(payment with initial submittal):

The applicant shall pay a site development permit application fee of $750. For projects associated with at least 4 residential units or affecting an area at least 1 acre, an additional fee of $1500 will be paid plus $150 per acre or fraction thereof.

Site Development, ROW, and Facilities Permit Fee
(payment prior to permit issuance):

The applicant shall pay a permit fee based on the final construction cost estimate prior to permit issuance as determined below.

Construction Cost Estimate Fees
$0–$10,000 7.5 percent of value
$10,000–$100,000 $750.00 plus 10 percent of value over $10,000
$100,000–$500,000 $9,750.00 plus 8 percent of value over $100,000
Over $500,000 $41,750.00 plus 5.5 percent of value over $500,000

[ TOP ]

Erosion Control Fees
(approximately 40% is Plan Review, 60% is Inspection)

A. Erosion control with a building permit
$0 to $25,000 $50
$25,001 to $50,000 $75
$50,001 to $100,000 $100
$100,001 and above $100 plus $75 per $100,000 or the fraction thereof exceeding the first $100,000

B. Erosion Control with no building permit
(part of a Site Development or ROW permit)
0 to 0.99 acre $250
1 acre and greater $250 plus $100/acre or fraction thereof.