Capital Improvements Projects

125th Ave Extension, Phase 2

Project Number: 3161

Project Description:
Provide storm water detention, water quality and wetland mitigation facilities near Green Ln and Hall Blvd. Phase 2 is coordinated with storm drainage projects resulting from the Blakeney Pond Drainage Study (Project No. 8033).

Project Status:
FY07-08: Begin project design and acquisition of right of way after the resolution of a Measure 37 claim by an adjacent property owner.

Required Substantial Completion Date: 09/30/2009

Project Maps:

Project Map


Murray Blvd Extension (Scholls Ferry Rd - Barrows Rd)

Project Number: 3229

Project Description:
This project completes the extension of Murray Blvd from Scholls Ferry Rd to Barrows Rd. The project includes two 12-foot wide travel lanes, a 12-foot wide turn lane at Springbrook Ln, two 12-foot wide turn lanes at Barrows Rd, two 10.5-foot wide sidewalks, a 300 foot long bridge, 600 lineal feet of retaining walls, 1700 lineal feet of 8-inch diameter waterline line, 1200 lineal feet of 12-inch storm drain, and landscaping and irrigation.

Project Status:
FY05-06: Complete design. FY06-07: Complete waterline installation and construct the section from the south bridge approach to Barrows Rd. FY07-08: Begin bridge construction.

Required Substantial Completion Date: 11/15/2007

Project Maps:

Project Map

Project Pictures:

Beginning project construction.

Beginning project construction.

Driving pile on south end.

Driving pile on south end.


Lombard (Broadway to Farmington) Realignment, MSTIP3

Project Number: 3306

Project Description:
Realign and widen approximately 572 feet of Lombard Ave between Broadway and Farmington Rd to 3 lanes and install curbs, bike lanes, planter strips, sidewalks, storm drainage, street lighting, and landscaping. This street project is being coordinated with the Commuter Rail (Wilsonville-Beaverton) project as shown on Exhibit A. Additional information on the Lombard street project is available at Washington County's Project Web Page and on the Commuter Rail project at Tri-Met's Commuter Rail Project Web Page.

Project Status:
This road project will be constructed together with Commuter Rail construction of which is underway. For updates on commuter Rail construction go to www.trimet.org/commterrail. The Lombard Ave realignment is scheduled to begin in the Spring of 2007. The former Wells Fargo Bank building was demolished in Feb 2007.

Required Substantial Completion Date: 09/30/2008

Project Maps:

Project Map


Franklin Ave Utility Improvements (2nd St - 12th St)

Project Number: 4010

Project Description:
Construct approximately 2400 feet of 8-inch waterline and asociated valves, hydrants, and water meters from 2nd St to 12th St.

Project Status:
FY07-08: Complete project design. FY08-09: Complete construction in the Summer of 2008.

Required Substantial Completion Date: 09/30/2008

Project Maps:

Project Map


Tigard Interconnect Master Meter No.2

Project Number: 4032A

Project Description:
Construct second water meter and piping between Beaverton and Tigard to increase the flow and pressure of potable water to Tigard. The water meter is proposed to be located at the intersection of Barrows Rd and Menlor Ln. The primary purpose of the project is to design and construct a pressure reducing station to increase capacity of water flow from the 550 top 450 pressure zone in Progress Ridge and areas adjacent to the Progress Ridge development during high demand periods such as firefighting and hot summer days.

Project Status:
FY07-08: A consultant is scheduled to design the PRV station and provide space and piping provisions for an interconnect with Master Meter No. 2. FY08-09: Begin construction in the Summer of 2008.

Required Substantial Completion Date: 10/30/2008

Project Maps:

Project Map


Allen Blvd (Lombard to Hall) Waterline Improvement, Phase 2

Project Number: 4049

Project Description:
The proposed project consists of the rehabilitation of approximately 1,829 lineal feet of 8-inch sanitary sewer pipe and 4,567 lineal feet of 4-inch and 6-inch sewer laterals, and upsizing of 1,318 lineal feet of sanitary sewer pipe on Allen Blvd (Hall Blvd to Alice Ln) in accordance with the 2004 Sanitary Sewer Master Plan, and construction of 1360 lineal feet of 16-inch ductile iron waterline and appurtenances on Allen Blvd (Lombard Ave to Hall Blvd) in accordance with the Water System Master Plan.

Project Status:
The project was advertised on 6-20-07, the mandatory pre-bid meeting was held on 6-22-07, and the bids were opened 7-10-07. Landis & Landis was the low bidder. Council is expected to award the project on 7-16-07, work to begin on 7-30-07, and the project to be substantially complete on 11-7-07. Clean Water Services is to pay for half of

Required Substantial Completion Date: 11/30/2007

Project Maps:

Project Map

Project Pictures:

Installing sanitary sewer manhole on Allen Blvd

Installing sanitary sewer manhole on Allen Blvd

Installing 6-inch HDPE sanitary sewer lateral at 12075 SW Allen Blvd

Installing 6-inch HDPE sanitary sewer lateral at 12075 SW Allen Blvd


Alger Ave Waterline Replacement/Upgrade

Project Number: 4073

Project Description:
Replace approximately 950 feet of 6-inch cast iron waterline with 12-inch ductile iron pipe on Alger Ave from 5th St to 9th St to include side street connections.

Project Status:
Project survey is complete. Design is underway and is scheduled to be complete in the Spring of 2007. Roto Rooter completed location of SS laterals on 313-07. Construction by City Forces is anticipated to begin in the Winter 2008.

Required Substantial Completion Date: 03/31/2008

Project Maps:

Project Map

Project Pictures:

Replace sanitary sewer laterals from 5th St to 9th St

Replace sanitary sewer laterals from 5th St to 9th St

Install 12" waterline from 5th St to 9th St

Install 12" waterline from 5th St to 9th St


Colony Ct Waterline Improvements

Project Number: 4074

Project Description:
Replace 600 feet of existing 2-inch galvanized waterline with 526 feet of new 6-inch waterline and 4 fire hydrants.

Project Status:
FY06-07: Complete design and begin construction in the late Spring 2007. FY07-08: Complete construction in early Summer 2007.

Required Substantial Completion Date: 07/31/2008

Project Maps:

Project Map


Railroad Crossing Improvement Watson Ave/Farmington Rd

Project Number: 5015H

Project Description:
Improve street RR crossing at Watson Ave and Farmington Rd in cooperation with Portland & Western Railroad.

Project Status:
Construction is scheduled for the Winter of 2007/08.

Required Substantial Completion Date: 06/30/2008

Project Maps:

Project Map


Oleson Rd (Fanno Creek - Hall Blvd), MSTIP3

Project Number: 5036

Project Description:
This MSTIP3 project includes two improved travel lanes, intersection and safety improvements, and bike and sidewalk facilities the length of the corridor. The project limits extend from approximately 575 feet north of SW Hall Boulevard to the south side of the Fanno Creek bridge, approximately 800 feet south of the intersection with the Beaverton-Hillsdale Hwy. This segment of SW Oleson Road is a Washington County minor arterial that runs through three jurisdictions: unincorporated Washington County, the City of Beaverton, and the City of Portland. The total project length is 2.63 miles.
For more information, see Washington County's Project Web Page.

Project Status:
Project construction of the South Section (Garden Home Rd to Hall Blvd) began in June 2006 and will continue through Oct 2007 with final paving scheduled for Oct 2008. Contractor is constructing a 16-inch waterline from Hall to Garden Home. Beginning in Jan 2007 NW Natural Gas will begin installation of a 6-inch gas line from Gardenm Home to BH Hwy and PGE will begin to relocate utility poles. Construction of the North Section (Garden Home Rd to Fanno Creek) is scheduled to begin in Oct 2007 and be complete in Nov 2008 to include final paving. Project is being managed by Washington County.

Required Substantial Completion Date: 11/30/2008

Project Maps:

Project Map


170th Ave/173rd Ave (Baseline Rd-Walker Rd), MSTIP3

Project Number: 5037

Project Description:
This MSTIP3 project includes approximately 3800 feet of street improvements on 170th Ave and 173rd Ave consisting of two 12-foot travel lanes, one 12-foot left turn lane, two 5-foot bike lanes , and two 6-foot sidewalks, and intersection and safety improvements.
For more information, see Washington County's Project Web Page.

Project Status:
6-2-03 Open House 1; 8-5-03 Partnering Session; 9-25-03 PAC mtg #1; 10-30-03 PAC mtg #2; 12-4-03 PAC mtg #3; 1-22-04 PAC mtg #4; 2-5-04 PAC mtg #5; 3-4-04 PAC mtg #6; 4-22-04 PAC mtg #7; 6-3-04 PAC mtg #8, PAC selected recommended alignment. 75% plans completed 9-16-05. 90% plans completed 2-21-06. Project schedule - Construction: Winter 2007 to Fall 2008. Project is being managed by Washington County.

Required Substantial Completion Date: 10/15/2007

Project Maps:

Project Map


Cornell Rd (Evergreen Pkwy to Bethany Blvd), MSTIP3B

Project Number: 5051

Project Description:
This project will rebuild and widen Cornell Road to five lanes from NW Evergreen Pkwy to NW 158th Ave. Work will include a portion of Bethany Blvd from Cornell Rd to the Hwy 26 (Sunset Hwy) right-of-way. Improvements will include bicycle lanes, curbs, sidewalks, landscape strips, three traffic signal modernizations, signing, striping and sound wall installations where appropriate.
For more information, see Washington County's Project Web Page.

Project Status:
Construction is anticipated to begin in the Spring of 2007 and be complete in the Fall 2008.

Required Substantial Completion Date: 09/30/2007

Project Maps:

Project Map


173rd Ave (Walker to Cornell) Street Lighting

Project Number: 5057

Project Description:
Installation of street lighting on 173rd. Ave from Walker Rd to Cornell Rd in order to meet minimum street lighting standards for the safety of motorists and pedestrians.

Project Status:
FY06-07: Complete project design. FY07-08: Compete installation of street lighting in the Spring 2008.

Required Substantial Completion Date: 06/30/2008

Project Maps:

Project Map


110th Ave Traffic Calming

Project Number: 5058

Project Description:
Provide traffic calming measures on 110th Ave from Center St to Cabot St in accordance with the City's Traffic Calming Program.

Project Status:
FY07/08: City staff to complete work with the neighborhood to prepare a traffic calming design. Gain approval of the design by the neighborhood, the Traffic Commission and City Council. FY08/09: Construction is anticipated in the Summer of 2008 by City Forces.

Required Substantial Completion Date: 09/30/2008

Project Maps:

Project Map


West Slope Sanitary Sewer Improvements

Project Number: 6018

Project Description:
Replace the following sanitary sewer lines: Lateral A (SSMH Y345 to SSMH Y348) and other lines to be determined through television inspection.

Project Status:
Design is scheduled for Summer of 2007 with construction scheduled for Spring and Summer of 2008. KCM, the engineering consultant that updated the Sanitary Sewer Master Plan, is confirming pipe size needs. Project was placed on hold in 2004 due to higher priorities elsewhere. Project is coordinated with CIP 8052.

Required Substantial Completion Date: 06/30/2008

Project Maps:

Project Map


Looking Glass Subdivision Utility Improvements

Project Number: 6039

Project Description:
Sanitary: Replace approximately 3,100 feet of 8-inch and 10-inch pipe with 10-inch and 12-inch pipe on various streets in the north Looking Glass Subdivision area. Storm drainage: Install aprox 1800 feet of 36-inch pipe on King Blvd, Duchess Wy and Alice Ln and a stormwater treatment vault on King Blvd. Water: Replace approximately 4200 feet of 6 inch and 8-inch water mains on Alice Ln, Duchess Ln, Tea Party Ci, Mad Hatter Ln, Why Worry Ln, and Griffin Pl. The above listed projects may change as a result of the site specific study of public utilities in the Looking Glass Subdivision area.

Project Status:
FY07/08: Complete study of the public utilities in the Looking Glass Subdivision area and make recommendation on the utilities to be replaced or rehabilitated and project phasing over multiple fiscal years if appropriate. Begin project design of Phase 1. FY08-09: Complete construction of Phase 1 and begin design of Phase 2 (if multiple phases are required).

Required Substantial Completion Date: 06/30/2008

Project Maps:

Project Map

Project Pictures:

Pipe Bursting - Drive rods being insterted into old pipe

Pipe Bursting - Drive rods being insterted into old pipe

Pipe Bursting - New pipe being pulled through old pipe

Pipe Bursting - New pipe being pulled through old pipe


South Central Area "C" Utility Improvements

Project Number: 6043

Project Description:
Sanitary: Rehabilitation of 5860 feet of sanitary pipe on Menlo Dr, Hazel St, Berthold St, Pearl St and 6th St in accordance with the Jan 2004 Sanitary Sewer Master Plan. Water: Replace and upsize 1300 feet of water line with 8-inch pipe on Hazel St between Erickson Ave and Menlo Dr in accordance with the Water System Master Plan.

Project Status:
Fall 2007: Complete survey and design. Winter/Spring FY07/08: Complete construction. The design of the waterline was done under Project No 4065.

Required Substantial Completion Date: 09/30/2008

Project Maps:

Project Map


Beaverton Creek Channel Enhancement (Hocken Ave - Cedar Hills Blvd)

Project Number: 8022B

Project Description:
Enhance approximately 800 LF of the Beaverton Creek channel between Hocken Ave and Cedar Hills Blvd. This project is for construction only. Project design was completed under Project 8022. The project includes removal of non-native vegetation such as blackberries, the installation of 10,000 SF of prefabricated modular retaining walls and a water quality swale, and the planting of hundreds of wetland plants, shrubs and trees.

Project Status:
FY05/06: Complete final design, specs and cost estimate and begin the process to obtain the necessary permits. 75% plans were completed 7-29-05. FY06/07: 90% plans were completed in Jan 2007. The Metro Nature in Neighborhoods Bond Measure was approved in Nov 2006. The amount of the bond measure funding allocated to this project is $500,000. Coordination continues with State and local agencies to obtain the necessary environmental permits and with adjacent property owners to obtain easements. FY07/08: Construction is scheduled to begin in the Summer of 2007 if in-water permits are obtained in time or in the summer of 2008.

Required Substantial Completion Date: 06/30/2008

Project Drawings:

Project Drawing (Large PDF File - 15 MB)

Project Maps:

Project Map

Project Pictures:

Project Benefit - Removal of blackberries & planting of native trees/shrubs

Project Benefit - Removal of blackberries & planting of native trees/shrubs

Project Benefit - Removal of shopping cart & other debris

Project Benefit - Removal of shopping cart & other debris


Park View Lp Storm Drain Improvements

Project Number: 8053

Project Description:
Pipe system improvements in the Greenway No. 3 Subdivision to address periodic flooding at the 8400 block of SW Park View Lp.

Project Status:
Project design is complete. Construction is contingent on resolution of issues with Tualatin Hills Park & Recreation District. If property impact issues can be resolved, then construction is anticipated in the Summer of 2007.

Required Substantial Completion Date: 09/30/2007

Project Maps:

Project Map

Project Pictures:

Flooding on Parkview Loop - April 2005.  Customer supplied photo.

Flooding on Parkview Loop - April 2005. Customer supplied photo.

Flooding on Parkview Loop - April 2005.  Customer supplied photo.

Flooding on Parkview Loop - April 2005. Customer supplied photo.


Betts Ave (2nd-Farmington) Storm Drain Improvement

Project Number: 8068

Project Description:
Replace 500 feet of 12-inch pipe and construct 3 manholes and 6 catchbasins.

Project Status:
Project is under design. Construction is anticipated to begin in the Spring of 2008.

Required Substantial Completion Date: 07/31/2008

Project Maps:

Project Map



Back to Capital Improvements Projects Map