CIP 4120 - Taralynn Ave Waterline Replacement

Taralynn Avenue Waterline Replacement Project

Project Description:

Replace 520 feet of 4-inch and 500 feet of 6-inch waterline with HDPE water pipe from Allen Blvd to end of cul-de-sac. 

Project Status:

  • 12-30-14: Design by staff is 50% complete. 
  • FY 15-16: Complete design. 
  • FY16-17: Complete construction. 

Substantial Completion Date: September 30, 2017 