CIP 4121/CIP 4132 - Kimberly Ct & 27th Ct Waterline Replacement

Kimberly Court & 27th Court Waterline Replacement Project

Project Description:

Replace 1000 feet of 6-inch pipe and associated structures. 

Project Manager:

Aaron Lee, 503-526-2446 

Project Status:

  • FY16-17: Survey and design by City. 
  • FY17-18: Complete construction 

Substantial Completion Date: October 30, 2017 

Image on a sunny day of driveway with surveyor's markings for waterline.