CIP 4122 - Alvord Ln Waterline Extension

Alvord Lane Waterline Extension Project

Project Description:

Install roughly 3100 feet of 16-inch DIP waterline from approximately SW 175th Ave to SW Siskin Ter as shown along the alignment highlighted in blue below. 

Project Manager:

Dave Winship, 503-526-2434 

Project Status: 

  • FY15-16: Begin preliminary design and coordinate easement options with adjacent property owners. 
  • FY16-17: Complete ROW coordination and begin construction. 
  • FY17-18: Complete construction. 

Substantial Completion Date: September 30, 2017 