Beaverdam Rd Improvement, Ph 2 - CIP 6073B

Beaverdam Road Waterline Improvement Project

Project Description:

Replace 1015 feet of 2-inch galvanized waterline with 8-inch ductile iron pipe and associated structures. 

Project Status:

CIP 6073B is phase 2 of the overall project to replace the existing pipe on Beaverdam Rd with an 8-inch ductile iron pipe. 6073A, phase 1, was completed by City Forces in Feb-Mar of 2016. 

  • FY15-16: Complete survey. 
  • FY16-17: Complete design and begin construction by contract. 

Substantial Completion Date: September 30, 2017 

CIP 6073B Description