CIP 3106A - Menlo Dr Sidewalk

Menlo Drive Sidewalk / Storm Drainage / Water Quality Improvements

Project Description: 

Design and construct a curb and sidewalk project along the east side of Menlo Dr from Fairmount Dr to Allen Blvd. The project also includes storm drainage and associated water quality improvements. The replacement of the existing street lighting system is included. The undergrounding of overhead utilities is not included. Public and private utilities may also be affected. The current total estimated cost of $1,920,000 is for 3,600 feet of sidewalk (one side of the street only). 

  • Engineering - $168,000
  • ROW - $118,000
  • Construction - $1,636,000

Project Manager: 

Luke Pelz, 503-526-2466 | Jim Brink, 503-526-2450 

Schedule: (as of July 1, 2018)

  • ROW Acquisition Complete (33 properties): May 7, 2018
  • Complete Design: July 31, 2018
  • Advertise: August 15, 2018
  • Bids Due: September 14, 2018
  • Award Contract: October 2, 2018
  • 22 Trees Removed: September 18 & 19, November 5, 2018
  • Begin Construction: November 28, 2018
  • Complete Construction: May 31, 2019

Substantial Completion Date: Spring 2019 

Man walking along roadway with no sidewalk and car backing out of driveway.