CIP 3106A - Menlo Dr Sidewalk

Menlo Drive Sidewalk / Storm Drainage / Water Quality Improvements

Project Description: 

Design and construct a curb and sidewalk project along the east side of Menlo Dr from Fairmount Dr to Allen Blvd. The project also includes storm drainage and associated water quality improvements. The replacement of the existing street lighting system is included. The undergrounding of overhead utilities is not included. Public and private utilities may also be affected. The cost per foot for a 5-foot wide separated from the curb by a 5-foot wide water quality swale is $370 which includes design and construction. The current total estimated cost of $1,716,000 is for 3,600 feet of sidewalk (one side of the street only). Right of Way acquisition will most likely be required and is included in the current estimated cost, as well as the cost for design. 

Project Manager: 

Luke Pelz, 503-526-2466 | Jim Brink, 503-526-2450 

Schedule: (as of July 1, 2018)

  • Complete Design: July 31, 2018
  • Advertise: August 1, 2018
  • Bids Due: August 22, 2018
  • Award Contract: September 3, 2018
  • Begin Construction: September 17, 2018
  • Complete Construction: Spring 2019

Substantial Completion Date: Spring 2019 

Man walking along roadway with no sidewalk and car backing out of driveway.