CIP 4116 - 6th Street Waterline Replacement

6th Street (Watson-Stott) Waterline Replacement 

Project Description:

Construct 825 feet of 6-inch waterline from Stott Ave to Watson Ave. The existing water main is a 2-inch galvanized pipe that is undersized and in need of replacement. In addition, the pipe requires upsizing to improve fire protection and to better support redevelopment. 

Project Manager:

Aaron Lee, 503-526-2446 

Project Status: 

  • FY17-18: Added to CIP in July 2017. 7-27-17: Begin design by city staff; 8-25-17: Completed design by city staff; 9-9-17: Council approved adding CIP 4116 to CIP 4134A, as a change order in the amount of $162,275; 9-28-17: Completed five potholes; 10-23-17: Begin construction by Trenchline Excavation. 

Substantial Completion Date: 06/30/2018 